(ANM) Sandy Lane

(ANM) Sandy Lane, Infinis Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 15 MW, grid supply point Warley.

Customer
Infinis Limited
Status
Accepted to connect
Capacity
15 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Warley
Bulk supply point
Purfleet Grid 33kV
Voltage
33 kV
Date accepted
8 May 2022
Target energisation
31 Oct 2036
In a connection queue
Yes
Row last updated by the DNO
12 Jul 2024
Licence area
EPN
Address
South Ockendon
Postcode
RM15 4XP

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.