(ANM - N/A) Raymonds Farm

(ANM - N/A) Raymonds Farm, BSR Applications Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 239.99 MW, grid supply point Rayleigh.

Customer
BSR Applications Limited
Status
Accepted to connect
Capacity
239.99 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
Yes (capacity not firm)
Grid supply point
Rayleigh
Point of connection
Rayleigh Main 132kV
Voltage
132 kV
Date accepted
27 Feb 2024
In a connection queue
Yes
Row last updated by the DNO
15 Apr 2024
Licence area
EPN
Address
London Road, Wickford
Postcode
SS11 8UA

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.