(ANM - N/A) Radwell Bury Farm East

(ANM - N/A) Radwell Bury Farm East, Balance Energy 5 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.95 MW, grid supply point Wymondley.

Customer
Balance Energy 5 Limited
Status
Accepted to connect
Capacity
49.95 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
Yes (capacity not firm)
Grid supply point
Wymondley
Voltage
132 kV
Date accepted
8 Apr 2023
Target energisation
31 Oct 2034
In a connection queue
Yes
Row last updated by the DNO
12 Jul 2024
Licence area
EPN
Address
Baldock
Postcode
SG7 5ES

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source