(ANM) Long Meadow Solar Farm
(ANM) Long Meadow Solar Farm, Low Carbon Solar Park 54 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 12 MW, grid supply point Pelham.
- Customer
- Low Carbon Solar Park 54 Limited
- Status
- Accepted to connect
- Capacity
- 12 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Pelham
- Bulk supply point
- Thaxted Grid 33kV
- Voltage
- 33 kV
- Date accepted
- 9 Feb 2022
- Target energisation
- 31 Oct 2032
- In a connection queue
- Yes
- Row last updated by the DNO
- 12 Jul 2024
- Licence area
- EPN
- Address
- Saffron Walden
- Postcode
- CB10 2SU
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.