Grid GuardianOpen the evidence in the app

(ANM) Linkhouse Farm

(ANM) Linkhouse Farm, Eclipse Power Networks Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.9 MW, grid supply point Rayleigh.

Customer
Eclipse Power Networks Limited
Status
Connected
Capacity
49.9 MW
Maximum import capacity
35 MW
Technology
Solar, Storage (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Rayleigh
Voltage
132 kV
Date connected
3 Dec 2025
In a connection queue
No
Row last updated by the DNO
16 Apr 2026
Licence area
EPN
Address
Church Road, Chelmsford
Postcode
CM2 8UN

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source