(ANM) Land South Of A47

(ANM) Land South Of A47, Vattenfall Networks UK, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.5 MW, grid supply point Norwich.

Customer
Vattenfall Networks UK
Status
Accepted to connect
Capacity
49.5 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Norwich
Voltage
132 kV
Date accepted
16 Oct 2020
Target energisation
31 Oct 2030
In a connection queue
Yes
Row last updated by the DNO
12 Jul 2024
Licence area
EPN
Address
Easton
Postcode
NR9 5DT

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.