Grid GuardianOpen the evidence in the app

(ANM) Land East Of B1256

(ANM) Land East Of B1256, Great Dunmow Power Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 7.5 MW, grid supply point Pelham.

Customer
Great Dunmow Power Limited
Status
Accepted to connect
Capacity
7.5 MW
Technology
Gas (Steam-gas turbine (CCGT))
Flexible connection
Yes (capacity not firm)
Grid supply point
Pelham
Bulk supply point
Thaxted Grid 33kV
Point of connection
Dunmow Primary 11kV
Voltage
11 kV
Date accepted
6 Mar 2021
Target energisation
31 Dec 2028
In a connection queue
Yes
Row last updated by the DNO
16 Jan 2023
Licence area
EPN
Address
Great Dunmow
Postcode
CM6 1EW

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.