Grid GuardianOpen the evidence in the app

(ANM) Land At Middlewick & Steeplewick

(ANM) Land At Middlewick & Steeplewick, Dengie Marshes Wind Farm Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 120 MW, grid supply point Rayleigh.

Customer
Dengie Marshes Wind Farm Limited
Status
Accepted to connect
Capacity
120 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
Yes (capacity not firm)
Grid supply point
Rayleigh
Voltage
132 kV
Date accepted
30 Nov 2023
In a connection queue
Yes
Row last updated by the DNO
15 Jan 2024
Licence area
EPN
Address
The Marshes, Southminster
Postcode
CM0 7JQ

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source