(ANM) Land At Balsam Fields
(ANM) Land At Balsam Fields, BSR Applications Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.99 MW, grid supply point Walpole.
- Customer
- BSR Applications Limited
- Status
- Accepted to connect
- Capacity
- 49.99 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Walpole
- Voltage
- 132 kV
- Date accepted
- 5 Sept 2025
- In a connection queue
- Yes
- Row last updated by the DNO
- 13 Jun 2025
- Licence area
- EPN
- Address
- Station Road, Kings Lynn
- Postcode
- PE34 4PL
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.