Grid GuardianOpen the evidence in the app

(ANM) Heydon Road

(ANM) Heydon Road, Grupotec Renewables Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 30 MW, grid supply point Norwich.

Customer
Grupotec Renewables Limited
Status
Accepted to connect
Capacity
30 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Norwich
Bulk supply point
Sall Grid 132/33kV
Voltage
33 kV
Date accepted
14 Aug 2024
In a connection queue
Yes
Row last updated by the DNO
13 Sept 2024
Licence area
EPN
Address
Norwich
Postcode
NR10 4SG

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source