Grid GuardianOpen the evidence in the app

(ANM) Eagle Business Park

(ANM) Eagle Business Park, Conrad Energy (Developments) Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 7.2 MW, grid supply point Walpole.

Customer
Conrad Energy (Developments) Limited
Status
Connected
Capacity
7.2 MW
Technology
Gas (Engine (combustion / reciprocating))
Flexible connection
Yes (capacity not firm)
Grid supply point
Walpole
Bulk supply point
Peterborough Central 33kV
Point of connection
Farcet Primary 11kV
Voltage
11 kV
In a connection queue
Yes
Row last updated by the DNO
14 Aug 2026
Licence area
EPN
Address
Yaxley
Postcode
PE7 3GP

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source