Grid GuardianOpen the evidence in the app

(ANM) Border Lane

(ANM) Border Lane, Gridsource, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 30 MW, grid supply point Norwich.

Customer
Gridsource
Status
Accepted to connect
Capacity
30 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Norwich
Bulk supply point
Gorleston Grid 33kV
Voltage
33 kV
Date accepted
22 Mar 2023
Target energisation
31 Oct 2034
In a connection queue
Yes
Row last updated by the DNO
15 Jan 2024
Licence area
EPN
Address
Yarmouth Road, Lowerstoff
Postcode
NR32 5LZ

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source