Acrows Energy Park
Acrows Energy Park, BIWO Renewables UK Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4.94 MW, grid supply point Pelham.
- Customer
- BIWO Renewables UK Limited
- Status
- Accepted to connect
- Capacity
- 4.94 MW
- Technology
- Onshore wind (Onshore wind turbines)
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Pelham
- Bulk supply point
- Thaxted Grid
- Point of connection
- Acrows Primary
- Voltage
- 11 kV
- Date accepted
- 21 Aug 2026
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Sept 2026
- Licence area
- EPN
- Address
- Ashdon Road, Saffron Waldon
- Postcode
- CB10 2NE
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.