Willington East 400kV Substation

Willington East 400kV Substation (NGET) has 4 projects in NESO's TEC Register of 23 Oct 2026: 401.9 MW in the queue, 401.9 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
4
MW in the queue
401.9 MW
Gate 1 MW
401.9 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage4401.9
Solar3344.9

Projects at Willington East 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Willington PV & BESSStorage, Solar249.9Gate 1Scoping31 Oct 2033
WillingtonStorage57Gate 1Scoping30 Jun 2026
Willington East 1 (Tertiary)Storage, Solar47.5Gate 1Scoping30 Oct 2027
Willington East 2 (Tertiary)Storage, Solar47.5Gate 1Scoping30 Jul 2028

Source