Willington East 1 (Tertiary)
Willington East 1 (Tertiary) is a storage, solar project of 47.5 MW in NESO's TEC Register of 23 Oct 2026, connecting at Willington East 400kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- ENSO GREEN HOLDINGS U LIMITED
- Connection site
- Willington East 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 47.5 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Oct 2027
- NESO project number
- PRO-000551
Also at Willington East 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Willington | Storage | 57 |
| Willington East 2 (Tertiary) | Storage, Solar | 47.5 |
| Willington PV & BESS | Storage, Solar | 249.9 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.