West Country Connection Node D 400kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 700 MW in the queue, 200 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
Transmission owner
NGET
Projects
2
MW in the queue
700 MW
Gate 1 MW
200 MW
MW connected
0 MW
By technology
Technology
Projects
MW
Storage
2
700
Onshore wind
1
500
Solar
1
500