Grid GuardianOpen the evidence in the app

Shurton BESS

Shurton BESS is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at West Country Connection Node D 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Field Shurton Ltd
Connection site
West Country Connection Node D 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2037
NESO project number
PRO-004248

Also at West Country Connection Node D 400kV Substation

ProjectTechnologyMW
Wick Moor DroveStorage, Solar, Onshore wind500

Source