Swansea North 400kV Substation

Swansea North 400kV Substation (NGET) has 9 projects in NESO's TEC Register of 23 Oct 2026: 2,021 MW in the queue, 698.9 MW Gate 1, and 61 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
9
MW in the queue
2,021 MW
Gate 1 MW
698.9 MW
MW connected
61 MW

By technology

TechnologyProjectsMW
Storage62,021
Solar31,674
Onshore wind21,274
Demand11,025
Reactive Compensation297
Gas261

Projects at Swansea North 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Swansea North Green Energy CentreDemand, Storage, Solar, Onshore wind400–1,025Scoping30 Oct 2028, 31 Oct 2033
SwanseaStorage, Solar400Gate 1Scoping31 Oct 2032
Hirfynydd and Mynydd DrumaurStorage, Solar, Onshore wind229.9–249Gate 1Scoping31 Oct 2030, 6 Dec 2036
BESS SwanStorage200Scoping31 Oct 2028
Swansea Greener Grid Park - Connection 1Storage, Reactive Compensation12–97Under Construction/Commissioning, Scoping31 Aug 2024, 31 Oct 2028
Swansea NorthStorage49.9Gate 1Scoping31 Jul 2028
Green Frog @ AlcoaGas40Built
Peak Gen LlandarcyGas21Built
Swansea Greener Grid Park - Connection 2Reactive Compensation0Consents Approved31 Jul 2025