Swansea North is a storage project of 49.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Swansea North 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
EDF ENERGY RENEWABLES LIMITED
Connection site
Swansea North 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
49.9 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Jul 2028
NESO project number
PRO-001119

Also at Swansea North 400kV Substation

ProjectTechnologyMW
BESS SwanStorage200
Green Frog @ AlcoaGas40
Hirfynydd and Mynydd DrumaurStorage, Solar, Onshore wind229.9–249
Peak Gen LlandarcyGas21
SwanseaStorage, Solar400
Swansea Greener Grid Park - Connection 1Storage, Reactive Compensation12–97
Swansea Greener Grid Park - Connection 2Reactive Compensation0
Swansea North Green Energy CentreDemand, Storage, Solar, Onshore wind400–1,025