Saltcoats 132/33kV
Saltcoats 132/33kV (SPT) has 2 projects in NESO's TEC Register of 23 Oct 2026: 130 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 2
- MW in the queue
- 130 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 2 | 130 |
Projects at Saltcoats 132/33kV
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Saltcoats NEP BESS Facility | Storage | 100 | Awaiting Consents | 31 Oct 2029 | |
| Meiklelaught Farm BESS | Storage | 30 | Scoping | 21 Aug 2028 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.