Saltcoats NEP BESS Facility

Saltcoats NEP BESS Facility is a storage project of 100 MW in NESO's TEC Register of 23 Oct 2026, connecting at Saltcoats 132/33kV (SPT). Status: Awaiting Consents.

Customer
Rashley New Energy Limited
Connection site
Saltcoats 132/33kV
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
100 MW
Agreement
Direct Connection
Status
Awaiting Consents
MW effective from
31 Oct 2029
NESO project number
PRO-002813