Grid GuardianOpen this site in the app

Ryhall 400kV Substation

Ryhall 400kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 790 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
790 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Solar2790
Storage1550

Projects at Ryhall 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Graeme Road Solar & BESSStorage, Solar550Scoping30 Oct 2038
EssendineSolar240Consents Approved1 Jan 2028