Essendine is a solar project of 240 MW in NESO's TEC Register of 23 Oct 2026, connecting at Ryhall 400kV Substation (NGET). Status: Consents Approved.
- Customer
- MALLARD PASS SOLAR FARM LIMITED
- Connection site
- Ryhall 400kV Substation
- Transmission owner
- NGET
- Technology
- Solar
- Capacity (TEC)
- 240 MW
- Agreement
- Direct Connection
- Status
- Consents Approved
- MW effective from
- 1 Jan 2028
- NESO project number
- PRO-001643