Grid GuardianOpen this site in the app

Roosecote 132kV Substation

Roosecote 132kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 49 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
0 MW
MW connected
49 MW

By technology

TechnologyProjectsMW
Storage149

Projects at Roosecote 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
RoosecoteStorage49Built