Roosecote

Roosecote is a storage project of 49 MW in NESO's TEC Register of 23 Oct 2026, connecting at Roosecote 132kV Substation (NGET). Status: Built.

Customer
CBS ENERGY STORAGE ASSETS UK LIMITED
Connection site
Roosecote 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
49 MW
Agreement
Embedded
Status
Built
NESO project number
PRO-000919