Nursling 400kV Substation
Nursling 400kV Substation (NGET) has 7 projects in NESO's TEC Register of 23 Oct 2026: 2,980 MW in the queue, 480 MW Gate 1, and 113.9 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 7
- MW in the queue
- 2,980 MW
- Gate 1 MW
- 480 MW
- MW connected
- 113.9 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Gas | 4 | 1,564 |
| Storage | 4 | 1,549 |
| Solar | 1 | 480 |
Projects at Nursling 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Nursling Flexible Generation | Gas | 1,500 | Scoping | 30 Oct 2038 | |
| NatPower Nursling Energy Park | Storage | 1,000 | Scoping | 31 Oct 2037 | |
| EPL Hampshire | Storage, Solar | 480 | Gate 1 | Scoping | 31 Oct 2037 |
| Nursling Tertiary | Storage | 49.9 | Built | ||
| Peak Gen Southampton | Gas | 24 | Built | ||
| Peak Gen Fareham | Gas | 21 | Built | ||
| Conrad (Winchester) Limited | Storage, Gas | 19 | Built |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.