Grid GuardianOpen the evidence in the app

NatPower Nursling Energy Park

NatPower Nursling Energy Park is a storage project of 1,000 MW in NESO's TEC Register of 23 Oct 2026, connecting at Nursling 400kV Substation (NGET). Status: Scoping.

Customer
SOUTHAMPTON ENERGY STORAGE LIMITED
Connection site
Nursling 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
1,000 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2037
NESO project number
PRO-004190

Also at Nursling 400kV Substation

ProjectTechnologyMW
Conrad (Winchester) LimitedStorage, Gas19
EPL HampshireStorage, Solar480
Nursling Flexible GenerationGas1,500
Nursling TertiaryStorage49.9
Peak Gen FarehamGas21
Peak Gen SouthamptonGas24

Source