Middleton 400KV Substation

Middleton 400KV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 840 MW in the queue, 200 MW of it Gate 2, 240 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
3
MW in the queue
840 MW
Gate 2 MW
200 MW
Gate 1 MW
240 MW
MW connected
0 MW
Earliest confirmed date
31 May 2029

By technology

TechnologyProjectsMW
Storage3840
Solar2640
Onshore wind1240

Projects at Middleton 400KV Substation

ProjectTechnologyMWGateStatusMW effective from
Heysham Green Energy CentreStorage, Solar400Awaiting Consents30 Oct 2028
Lightsource MiddletonStorage, Solar, Onshore wind240Gate 1Scoping30 Oct 2037
Middleton BESSStorage200Gate 2Under Construction/Commissioning31 May 2029