Middleton BESS

Middleton BESS is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Middleton 400KV Substation (NGET). Status: Under Construction/Commissioning. Gate 2.

Customer
Middleton Energy Storage Limited
Connection site
Middleton 400KV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 2
Status
Under Construction/Commissioning
MW effective from
31 May 2029
NESO project number
PRO-002305

Also at Middleton 400KV Substation

ProjectTechnologyMW
Heysham Green Energy CentreStorage, Solar400
Lightsource MiddletonStorage, Solar, Onshore wind240