Ladyburn 132kV Substation
Ladyburn 132kV Substation (SPT) has 3 projects in NESO's TEC Register of 23 Oct 2026: 266 MW in the queue, 96 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 3
- MW in the queue
- 266 MW
- Gate 1 MW
- 96 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 3 | 266 |
| Storage | 2 | 206 |
Projects at Ladyburn 132kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Craiglarie Wind Farm | Storage, Onshore wind | 170 | Scoping | 31 Oct 2037 | |
| D&G 2 | Onshore wind | 60 | Gate 1 | Scoping | 29 Aug 2031 |
| Craig Nab Wind Energy Hub | Storage, Onshore wind | 36 | Gate 1 | Scoping | 29 Aug 2031 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.