D&G 2
D&G 2 is a onshore wind project of 60 MW in NESO's TEC Register of 23 Oct 2026, connecting at LADYBURN 132/33KV GRID SUPPLY POINT SUBSTATION (SPT). Status: Scoping. Gate 1.
- Customer
- Greyland Energy Park Limited
- Connection site
- LADYBURN 132/33KV GRID SUPPLY POINT SUBSTATION
- Transmission owner
- SPT
- Technology
- Onshore wind
- Capacity (TEC)
- 60 MW
- Agreement
- Embedded
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 29 Aug 2031
- NESO project number
- PRO-004772
Also at LADYBURN 132/33KV GRID SUPPLY POINT SUBSTATION
| Project | Technology | MW |
|---|---|---|
| Craig Nab Wind Energy Hub | Storage, Onshore wind | 36 |
| Craiglarie Wind Farm | Storage, Onshore wind | 170 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.