Kintore GSP

Kintore GSP (SHET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 2,140 MW in the queue, 40 MW of it Gate 2, 1,800 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
3
MW in the queue
2,140 MW
Gate 2 MW
40 MW
Gate 1 MW
1,800 MW
MW connected
0 MW
Earliest confirmed date
31 Oct 2029

By technology

TechnologyProjectsMW
Interconnector11,800
Offshore wind11,800
Storage1300
Energy from waste140

Projects at Kintore GSP

ProjectTechnologyMWGateStatusMW effective from
North-East Offshore Hybrid AssetInterconnector, Offshore wind1,800Gate 1Scoping30 Jun 2037
Alcemi Midmill BESSStorage300Scoping31 Dec 2029
Thainstone Energy ParkEnergy from waste40Gate 2Consents Approved31 Oct 2029