North-East Offshore Hybrid Asset
North-East Offshore Hybrid Asset is a interconnector, offshore wind project of 1,800 MW in NESO's TEC Register of 23 Oct 2026, connecting at Kintore GSP (SHET). Status: Scoping. Gate 1.
- Customer
- National Grid Interconnector Holdings Limited
- Connection site
- Kintore GSP
- Transmission owner
- SHET
- Technology
- Interconnector, Offshore wind
- Capacity (TEC)
- 1,800 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Jun 2037
- NESO project number
- PRO-004942
Also at Kintore GSP
| Project | Technology | MW |
|---|---|---|
| Alcemi Midmill BESS | Storage | 300 |
| Thainstone Energy Park | Energy from waste | 40 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.