Kingsnorth 400kV Substation
Kingsnorth 400kV Substation (NGET) has 7 projects in NESO's TEC Register of 23 Oct 2026: 3,030 MW in the queue, 1,120 MW Gate 1, and 812 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 7
- MW in the queue
- 3,030 MW
- Gate 1 MW
- 1,120 MW
- MW connected
- 812 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 6 | 3,030 |
| Gas | 2 | 2,612 |
| Demand | 1 | 500 |
| Solar | 2 | 180 |
| Onshore wind | 1 | 60 |
Projects at Kingsnorth 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Damhead Creek 2 | Gas, Storage | 1,800 | Consents Approved | 31 Oct 2030 | |
| Damhead Creek | Gas | 812 | Built | ||
| Kingsnorth BESS NP | Storage | 500 | Gate 1 | Scoping | 31 Dec 2030 |
| Medway 3 Power Station | Demand, Storage | 500 | Gate 1 | Scoping | 30 Apr 2032 |
| Kingsnorth | Storage, Solar | 120 | Gate 1 | Scoping | 31 Oct 2028 |
| Rochester Renewable Project | Storage, Solar, Onshore wind | 60 | Scoping | 22 Sept 2028 | |
| Cuxton 49.5MW BESS | Storage | 49.5 | Consents Approved | 31 May 2023 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.