Cuxton 49.5MW BESS
Cuxton 49.5MW BESS is a storage project of 49.5 MW in NESO's TEC Register of 23 Oct 2026, connecting at Kingsnorth 400kV Substation (NGET). Status: Consents Approved.
- Customer
- Cuxton Energy Storage Limited
- Connection site
- Kingsnorth 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 49.5 MW
- Agreement
- Embedded
- Status
- Consents Approved
- MW effective from
- 31 May 2023
- NESO project number
- PRO-002373
Also at Kingsnorth 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Damhead Creek | Gas | 812 |
| Damhead Creek 2 | Gas, Storage | 1,800 |
| Kingsnorth | Storage, Solar | 120 |
| Kingsnorth BESS NP | Storage | 500 |
| Medway 3 Power Station | Demand, Storage | 500 |
| Rochester Renewable Project | Storage, Solar, Onshore wind | 60 |