Harker 400kV Substation
Harker 400kV Substation (NGET) has 9 projects in NESO's TEC Register of 23 Oct 2026: 2,694 MW in the queue, 546.9 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 9
- MW in the queue
- 2,694 MW
- Gate 1 MW
- 546.9 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 8 | 2,544 |
| Solar | 5 | 1,882 |
| Onshore wind | 1 | 1,025 |
Projects at Harker 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Harker Green Energy Centre | Storage, Solar, Onshore wind | 400–1,025 | Awaiting Consents | 30 Oct 2028, 30 Oct 2032 | |
| Low Harker BESS | Storage, Solar | 400 | Scoping | 30 Nov 2037 | |
| ESB Harker BESS | Storage | 342 | Scoping | 31 Oct 2039 | |
| Harker PV & BESS Sub | Storage, Solar | 249.9 | Gate 1 | Scoping | 1 Nov 2037 |
| NEL Story | Storage | 240 | Gate 1 | Scoping | 30 Nov 2037 |
| BESS Harker | Storage | 200 | Consents Approved | 30 May 2031 | |
| RIGG HOUSE PV FARM | Solar | 150 | Scoping | 31 Oct 2037 | |
| Pivot Power Harker Hybrid | Storage, Solar | 57 | Gate 1 | Scoping | 31 Oct 2029 |
| Barrow | Storage | 30 | Scoping | 31 Oct 2037 |
Source