Low Harker BESS

Low Harker BESS is a storage, solar project of 400 MW in NESO's TEC Register of 23 Oct 2026, connecting at Harker 400kV Substation (NGET). Status: Scoping.

Customer
Energi Generation 14 Ltd
Connection site
Harker 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
400 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
30 Nov 2037
NESO project number
PRO-003873

Also at Harker 400kV Substation

ProjectTechnologyMW
BarrowStorage30
BESS HarkerStorage200
ESB Harker BESSStorage342
Harker Green Energy CentreStorage, Solar, Onshore wind400–1,025
Harker PV & BESS SubStorage, Solar249.9
NEL StoryStorage240
Pivot Power Harker HybridStorage, Solar57
RIGG HOUSE PV FARMSolar150

Source