Greens 400kV Substation
Greens 400kV Substation (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 3,500 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 2
- MW in the queue
- 3,500 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Offshore wind | 2 | 3,500 |
Projects at Greens 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Caledonia Offshore Wind Farm | Offshore wind | 600–2,000 | Scoping | 31 Mar 2031, 31 Oct 2032 | |
| Stromar Offshore Windfarm | Offshore wind | 1,000–1,500 | Scoping | 31 Oct 2033, 31 Dec 2035 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.