Caledonia Offshore Wind Farm

Caledonia Offshore Wind Farm is a offshore wind project of 600–2,000 MW in NESO's TEC Register of 23 Oct 2026, connecting at Greens 400kV Substation (SHET). Status: Scoping.

Customer
CALEDONIA OFFSHORE WIND FARM LIMITED
Connection site
Greens 400kV Substation
Transmission owner
SHET
Technology
Offshore wind
Capacity (TEC)
600–2,000 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Mar 2031, 31 Oct 2032
NESO project number
PRO-001436-1, PRO-001436-2