Eccles 400/132kV
Eccles 400/132kV (SPT) has 6 projects in NESO's TEC Register of 23 Oct 2026: 1,380 MW in the queue, 900 MW of it Gate 2, 430.56 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 6
- MW in the queue
- 1,380 MW
- Gate 2 MW
- 900 MW
- Gate 1 MW
- 430.56 MW
- MW connected
- 0 MW
- Earliest confirmed date
- 12 Apr 2026
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 5 | 1,340 |
| Solar | 1 | 40.56 |
Projects at Eccles 400/132kV
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Eccles BESS | Storage | 500 | Gate 2 | Under Construction/Commissioning | 12 Apr 2026 |
| Zenobe Eccles Battery Storage | Storage | 400 | Gate 2 | Under Construction/Commissioning | 30 Apr 2026 |
| Pittlesheugh Farm | Storage | 340 | Gate 1 | Scoping | 31 Oct 2030 |
| Coldstream BESS | Storage | 50 | Gate 1 | Scoping | 31 Oct 2030 |
| AMP Eccles BESS | Storage | 49.9 | Scoping | 31 Oct 2029 | |
| Coldstream Solar PV Plant | Solar | 40.56 | Gate 1 | Scoping | 31 Jul 2031 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.