Grid GuardianOpen the evidence in the app

Eccles BESS

Eccles BESS is a storage project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Eccles 400kV Substation (SPT). Status: Under Construction/Commissioning. Gate 2.

Customer
Eccles Energy Centre Limited
Connection site
Eccles 400kV Substation
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
500 MW
Agreement
Direct Connection
Gate
Gate 2
Status
Under Construction/Commissioning
MW effective from
12 Apr 2026
NESO project number
PRO-001470

Also at Eccles 400kV Substation

ProjectTechnologyMW
AMP Eccles BESSStorage49.9
Coldstream BESSStorage50
Coldstream Solar PV PlantSolar40.56
Pittlesheugh FarmStorage340
Zenobe Eccles Battery StorageStorage400

Source