Derbyshire Connection Node I 400kV Substation

Derbyshire Connection Node I 400kV Substation (NGET) has 4 projects in NESO's TEC Register of 23 Oct 2026: 1,518 MW in the queue, 1,518 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
4
MW in the queue
1,518 MW
Gate 1 MW
1,518 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage41,518
Solar2740

Projects at Derbyshire Connection Node I 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Elmya Towcester BESSStorage550Gate 1Scoping30 Oct 2037
Long Buckby Solar/BESSStorage, Solar500Gate 1Scoping30 Oct 2037
Lightsource Patford BridgeStorage, Solar240Gate 1Scoping30 Oct 2037
Patford Bridge BESSStorage228Gate 1Scoping30 Oct 2037