Elmya Towcester BESS

Elmya Towcester BESS is a storage project of 550 MW in NESO's TEC Register of 23 Oct 2026, connecting at Derbyshire Connection Node I 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
RPC ELMYA CARNATION TOWCESTER LIMITED
Connection site
Derbyshire Connection Node I 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
550 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2037
NESO project number
PRO-004809

Also at Derbyshire Connection Node I 400kV Substation

ProjectTechnologyMW
Lightsource Patford BridgeStorage, Solar240
Long Buckby Solar/BESSStorage, Solar500
Patford Bridge BESSStorage228