Chickerell 400kV Substation

Chickerell 400kV Substation (NGET) has 5 projects in NESO's TEC Register of 23 Oct 2026: 3,450 MW in the queue, 400 MW of it Gate 2, 3,050 MW Gate 1, and 47 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
5
MW in the queue
3,450 MW
Gate 2 MW
400 MW
Gate 1 MW
3,050 MW
MW connected
47 MW
Earliest confirmed date
31 Oct 2028

By technology

TechnologyProjectsMW
Storage43,450
Solar22,900
Offshore wind12,500
CHP (Combined Heat and Power)147

Projects at Chickerell 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
PortwindStorage, Solar, Offshore wind2,500Gate 1Scoping6 Dec 2036
ChickerellStorage, Solar200–400Gate 1Awaiting Consents6 Dec 2036, 31 Oct 2037, 31 Oct 2038
Chickerell Solar PV & BESSStorage400Gate 2Consents Approved31 Oct 2028
BESS North FarmStorage150Gate 1Scoping1 Nov 2031
ChickerellCHP (Combined Heat and Power)47Built