Grid GuardianOpen the evidence in the app

Chickerell Solar PV & BESS

Chickerell Solar PV & BESS is a storage project of 400 MW in NESO's TEC Register of 23 Oct 2026, connecting at Chickerell 400kV Substation (NGET). Status: Consents Approved. Gate 2.

Customer
CHICKERELL STORAGE LIMITED
Connection site
Chickerell 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
400 MW
Agreement
Direct Connection
Gate
Gate 2
Status
Consents Approved
MW effective from
31 Oct 2028
NESO project number
PRO-001598

Also at Chickerell 400kV Substation

ProjectTechnologyMW
BESS North FarmStorage150
ChickerellStorage, Solar200–400
ChickerellCHP (Combined Heat and Power)47
PortwindStorage, Solar, Offshore wind2,500