Butlers Wood 400kV Substation
Butlers Wood 400kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 1,355 MW in the queue, 330 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 2
- MW in the queue
- 1,355 MW
- Gate 1 MW
- 330 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 2 | 1,355 |
| Solar | 1 | 1,025 |
Projects at Butlers Wood 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Butlers Wood Green Energy Centre | Storage, Solar | 1,025 | Awaiting Consents | 30 Oct 2031 | |
| Zenobe Butler's Wood BESS | Storage | 330 | Gate 1 | Scoping | 31 Oct 2034 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.