Zenobe Butler's Wood BESS

Zenobe Butler's Wood BESS is a storage project of 330 MW in NESO's TEC Register of 23 Oct 2026, connecting at Butlers Wood 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
ZENOBE ENERGY LIMITED
Connection site
Butlers Wood 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
330 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2034
NESO project number
PRO-004085