Bridgwater 400/132kV Substation
Bridgwater 400/132kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 306.99 MW in the queue, and 6 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 3
- MW in the queue
- 306.99 MW
- MW connected
- 6 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 2 | 306.99 |
| Solar | 1 | 57 |
| Gas | 1 | 6 |
Projects at Bridgwater 400/132kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Bridgwater Energy Park | Storage | 249.99 | Scoping | 31 Oct 2037 | |
| Bridgwater (tertiary) | Storage, Solar | 57 | Scoping | 31 Aug 2028 | |
| Green frog @ The Drove | Gas | 6 | Built |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.