Bridgwater 400/132kV Substation

Bridgwater 400/132kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 306.99 MW in the queue, and 6 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
3
MW in the queue
306.99 MW
MW connected
6 MW

By technology

TechnologyProjectsMW
Storage2306.99
Solar157
Gas16

Projects at Bridgwater 400/132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Bridgwater Energy ParkStorage249.99Scoping31 Oct 2037
Bridgwater (tertiary)Storage, Solar57Scoping31 Aug 2028
Green frog @ The DroveGas6Built