Bridgwater (tertiary)
Bridgwater (tertiary) is a storage, solar project of 57 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bridgwater 400/132kV Substation (NGET). Status: Scoping.
- Customer
- ENSO GREEN HOLDINGS H LIMITED
- Connection site
- Bridgwater 400/132kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 57 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 31 Aug 2028
- NESO project number
- PRO-000375
Also at Bridgwater 400/132kV Substation
| Project | Technology | MW |
|---|---|---|
| Bridgwater Energy Park | Storage | 249.99 |
| Green frog @ The Drove | Gas | 6 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.