Bramford B 400kV Substation

Bramford B 400kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 650 MW in the queue, 650 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
650 MW
Gate 1 MW
650 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Solar1650
Storage1650

Projects at Bramford B 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Bramford GEC (Ethos Green)Storage, Solar650Gate 1Awaiting Consents1 Jun 2032